Abstract: Based on an engineering case, 2D and 3D finiteelement tools were employed to analyze the mutual impact of constructing hand-dug piles close to retaining wall. Combined with the analysis data, some measures were implemented. The results show that the hand-dug piles have obvious space arch effect. When the net distance between 3 meter diameter handdug piles and retaining wall is 5 meters, only simple design measures are needed to ensure the safety of the foundation pit.
 

Key words: foundation pit, hand-dug pile, construction, numerical analysis