Load Characteristics and Optimal Layout of Center and Gage Cutters of Rock Formation Compound Tunnel Boring Machine

  • 张康健,胡哲钏,张志强
Expand
  • (Key Laboratory of Transportation Tunnel Engineering of Ministry of Education, Chengdu 610031, China; School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, China)

Received date: 2021-07-13

  Accepted date: 2021-11-16

  Online published: 2024-09-28

Abstract

The cutter layout of a full-face tunnel boring machine (TBM) directly affects its tunneling efficiency. The revolving diameter of the center cutter is small, and the double-edged design results in its rock breaking mechanism and force characteristics being significantly different from those of the single-edged cutter. The gage cutter is installed on the transition arc of the cutterhead, and the installation inclination complicates its movement and force. In this paper, by taking sandstone as the research object, the composite rock breaking models of the center cutter group and the gage cutter group of a compound TBM are separately established based on the three-dimensional particle discrete element method. The numerical models are verified by comparing results with the full-scale rotary cutting laboratory test. From the view point of the force characteristics of a single cutter, the propagation of rock cracks between adjacent cutters, the overall mechanical properties of the cutterhead, the load characteristics and layout form of the double-edged center cutter, and the installation angle range of the gage cutter were studied. Results demonstrate that the use of a cross-shaped center cutter layout can reduce the force of a single cutter ring and the overall load of the cutterhead, which is conducive to TBM stability during tunneling. Therefore, it is recommended that a cross-shaped layout for the double-edged center cutter of a rock formation compound TBM should be used. To improve the stability and service life of the cutter, we recommend setting the installation angle of the innermost gage cutter of the rock formation compound TBM to about 9◦, and the installation angle of the outermost gage cutter should not exceed 70◦.

Cite this article

张康健,胡哲钏,张志强 . Load Characteristics and Optimal Layout of Center and Gage Cutters of Rock Formation Compound Tunnel Boring Machine[J]. Journal of Shanghai Jiaotong University(Science), 2024 , 29(5) : 857 -875 . DOI: 10.1007/s12204-022-2532-4

References

[1] ROSTAMI J, CHANG S H. A closer look at the design of cutterheads for hard rock tunnel-boring machines[J]. Engineering, 2017, 3(6): 892-904.
[2] ENTACHER M, WINTER G, GALLER R. Cutter force measurement on tunnel boring machinesImplementation at Koralm tunnel [J]. Tunnelling and Underground Space Technology, 2013, 38: 487-496.
[3] HUO J Z, SUN W, CHEN J, et al. Disc cutters plane layout design of the full-face rock tunnel boring machine (TBM) based on different layout patterns[J]. Computers & Industrial Engineering, 2011, 61(4):1209-1225.
[4] LAN H, XIA Y M, MIAO B, et al. Prediction model of wear rate of inner disc cutter of engineering in Yinsong, Jilin [J]. Tunnelling and Underground Space Technology, 2020, 99: 103338.
[5] GENG Q, WEI Z Y, HE F, et al. Comparison of the mechanical performance between two-stage and flatface cutter head for the rock tunnel boring machine(TBM) [J]. Journal of Mechanical Science and Technology, 2015, 29(5): 2047-2058.
[6] FANG Y, YAO Z G, XU W H, et al. The performance of TBM disc cutter in soft strata: A numerical simulation using the three-dimensional RBD-DEM coupled method [J]. Engineering Failure Analysis, 2021, 119: 104996.
[7] ROSTAMI J. Study of pressure distribution within the crushed zone in the contact area between rock and disccutters [J]. International Journal of Rock Mechanics and Mining Sciences, 2013, 57: 172-186.
[8] BALCI C. Correlation of rock cutting tests with field performance of a TBM in a highly fractured rock formation: A case study in Kozyatagi-Kadikoy metro tunnel, Turkey [J]. Tunnelling and Underground Space Technology, 2009, 24(4): 423-435.
[9] LIU J Q, REN J B, GUO W. Thrust and torque characteristics based on a new cutter-head load model[J]. Chinese Journal of Mechanical Engineering, 2015,28(4): 801-809.
[10] YANG K, XIA Y M, WU Y. Studies on rock-breaking of positive disc cutter and edge disc cutter [J]. Applied Mechanics and Materials, 2014, 508: 159-164.
[11] YIN L J, MIAO C T, HE G W, et al. Study on the influence of joint spacing on rock fragmentation under TBM cutter by linear cutting test [J]. Tunnelling and Underground Space Technology, 2016, 57: 137-144.
[12] ENTACHER M, SCHULLER E, GALLER R. Rock failure and crack propagation beneath disc cutters [J].Rock Mechanics and Rock Engineering, 2015, 48(4):1559-1572.
[13] LI G, WANG B, CHEN Y D, et al. Numerical simulation of the rock fragmentation process induced bTBM cutters [J]. Applied Mechanics and Materials,2013, 249/250: 1069-1072.
[14] CHO J W, JEON S, YU S H, et al. Optimum spacing of TBM disc cutters: A numerical simulation using the three-dimensional dynamic fracturing method [J]. Tunnelling and Underground Space Technology, 2010,25(3): 230-244.
[15] ZHU X H, XIA Y M, OUYANG T, et al. Distribution law of excavating load of TBM disc cutter and cutterhead [J]. Applied Mechanics and Materials, 2014, 615:22-26.
[16] ZHANG X H, XIA Y M, LIU J, et al. Study on characteristics of breaking rock by double edge central disc cutter under confining pressure [J]. Journal of Northeastern University (Natural Science), 2017,38(6): 839-844 (in Chinese).
[17] SUN J, CHEN M, CHEN B, et al. Numerical simulaiton of influence factors for rock fragmentation by TBM cutter [J]. Rock and Soil Mechanics, 2011, 32(6):1891-1897 (in Chinese).
[18] TAN Q, LI J, XIA Y, et al. Numerical research on rock fragmentation process by disc cutter[J]. Rock and Soil Mechanics, 2013, 34(9): 2707-2714 (in Chinese).
[19] REN D J, SHEN J S, CHAI J C, et al. Analysis of disccutter failure in shield tunnelling using 3D circular cutting theory [J]. Engineering Failure Analysis, 2018,90: 23-35.
[20] ENTACHER M, WINTER G, BUMBERGER T, et al. Cutter force measurement on tunnel boring machines -System design [J]. Tunnelling and Underground Space Technology, 2012, 31: 97-106.
[21] HUANG X, LIU Q, CHEN L, et al. Cutting force measurement and analyses of shell cutters on a mixshield tunnelling machine [J]. Tunnelling and Underground Space Technology, 2018, 82: 325-345.
[22] HUO J Z, WANG W Z, SUN W, et al. The multi-stage rock fragmentation load prediction model of tunnel boring machine cutter group based on dense core theory [J]. The International Journal of Advanced Manufacturing Technology, 2017, 90(1/2/3/4): 277-289.
[23] XU H G, GENG Q, SUN Z C, et al. Full-scale granite cutting experiments using tunnel boring machine disc cutters at different free-face conditions [J]. Tunnelling and Underground Space Technology, 2021,108: 103719.
[24] GENG Q, WEI Z Y, REN J H. New rock material definition strategy for FEM simulation of the rock cutting process by TBM disc cutters [J]. Tunnelling and Underground Space Technology, 2017, 65: 179-186.
[25] GENG Q, WEI Z Y, MENG H, et al. Mechanical performance of TBM cutterhead in mixed rock ground conditions [J]. Tunnelling and Underground Space Technology, 2016, 57: 76-84.
[26] ZHUO X J, LI P Q, HE F. Development of TBM boring test bench [J]. Tunnel Construction, 2013, 33(7): 615-618 (in Chinese).
[27] WU Y, XIA Y, GUO J, et al. Influence of key parameters of a TBM gauge disc cutter on rock-breaking efficiency[J]. Modern Tunnelling Technology, 2015, 52(1):119-126 (in Chinese).
[28] GENG Q, WEI Z Y, MENG H. An experimental research on the rock cutting process of the gage cutters for rock tunnel boring machine (TBM) [J]. Tunnelling and Underground Space Technology, 2016, 52: 182-191.
[29] ZHANG Z H, MENG L, SUN F. Rock deformation equations and application to the study on slantingly installed disc cutter [J]. Acta Mechanica Sinica, 2014,30(4): 540-546.
[30] XIA Y, WU Y, GUO J, et al. Numerical simulation of rock-breaking mechanism by gage disc cutter of TBM[J]. Journal of China Coal Society, 2014, 39(1):172-178 (in Chinese).
[31] Ministry of Housing and Urban-Rural Development of the People’s Republic of China. Standard for test methods of engineering rock mass: GB/T 50266—2013[S]. Beijing: China Planning Press, 2013 (in Chinese).
[32] Ministry of Water Resources of the People’s Republic of China. Code for rock tests in water and hydropower projects: SL/T 264—2020 [S]. Beijing: China Water & Power Press, 2020 (in Chinese).
[33] POTYONDY D O, CUNDALL P A. A bonded-particle model for rock [J]. International Journal of Rock Mechanics and Mining Sciences, 2004, 41(8): 1329-1364.
[34] ZHANG Z Q, ZHANG K J, DONG W J, et al. Study of rock-cutting process by disc cutters in mixed ground based on three-dimensional particle flow model [J]. Rock Mechanics and Rock Engineering, 2020, 53(8):3485-3506.
[35] ASADI M S, RASOULI V, BARLA G. A bonded particle model simulation of shear strength and asperity degradation for rough rock fractures [J]. Rock Mechanics and Rock Engineering, 2012, 45(5): 649-675.
[36] GHAZVINIAN A, SARFARAZI V, SCHUBERT W, et al. A study of the failure mechanism of planar nonpersistent open joints using PFC2D [J]. Rock Mechanics and Rock Engineering, 2012, 45(5): 677-693.
[37] LEE H, JEON S. An experimental and numerical study of fracture coalescence in pre-cracked specimens under uniaxial compression [J]. International Journal of Solids and Structures, 2011, 48(6): 979-999.
[38] POTYONDY D O. The bonded-particle model as a tool for rock mechanics research and application: Current trends and future directions [J]. Geosystem Engineering, 2015, 18(1): 1-28.
[39] TAROKH A, FAKHIMI A. Discrete element simulation of the effect of particle size on the size of fracture process zone in quasi-brittle materials [J]. Computers and Geotechnics, 2014, 62: 51-60.
[40] WENG M C, LI H H. Relationship between the deformation characteristics and microscopic properties of sandstone explored by the bonded-particle model [J]. International Journal of Rock Mechanics and Mining Sciences, 2012, 56: 34-43.
[41] ZHANG X P, WONG L N Y. Crack initiation, propagation and coalescence in rock-like material containing two flaws: A numerical study based on bonded-particle model approach [J]. Rock Mechanics and Rock Engineering, 2013, 46(5): 1001-1021.
[42] CHO N, MARTIN C D, SEGO D C. A clumped particle model for rock [J]. International Journal of Rock Mechanics and Mining Sciences, 2007, 44(7): 997-1010.
[43] JIANG M J, FANG W, SIMA J. Calibration of micro-parameters of parallel bonded model for rocks [J]. Journal of Shandong University (Engineering Science), 2015, 45(4): 50-56 (in Chinese).
[44] WU L, GUAN T M, LEI L. Discrete element model for performance analysis of cutterhead excavation system of EPB machine [J]. Tunnelling and Underground Space Technology, 2013, 37: 37-44.