Journal of Shanghai Jiaotong University >
Risk and Preventive Measures of Pile Placement in Chengdao Oilfield
Received date: 2022-07-07
Revised date: 2022-07-25
Accepted date: 2022-08-22
Online published: 2023-11-10
Chengdao Oilfield is located in the modern Yellow River underwater delta, where the seabed strata are complex, and the sediment silt and silty clay have great interbedding changes. In recent years, an increasing number of jack-ups are installed and removed in the same wellhead or similar wellhead. There are risks of sliding pile, punch-through, and liquefaction and subsidence in the area where piles are repeatedly inserted and pulled out on offshore moving platform. Aimed at the risks, preventive measures are analyzed to reduce the risk of pile driving on jack-up platforms.
AN Tao, LIN Zengyong, ZHANG Da . Risk and Preventive Measures of Pile Placement in Chengdao Oilfield[J]. Journal of Shanghai Jiaotong University, 2023 , 57(S1) : 25 -29 . DOI: 10.16183/j.cnki.jsjtu.2023.S1.09
[1] | 国家能源局. 海洋井场调查规范: SY/T 6707—2016[S]. 北京: 石油工业出版社, 2016. |
[1] | National Energy Administration. Specification for marine well site survey: SY/T 6707—2016[S]. Beijing: Petroleum Industry Press, 2016. |
[2] | ISO 19905-1. Petroleum and natural gas industries-site-specific assessment of mobile offshore units-part 1: jack-ups[S]. Geneva: International Organization for Standardization, 2016. |
[3] | ISO 19905-1: 2016. Guidelines for site specific assessment of mobile jack-up units[S]. New Jersey, USA: SNAME, 2002. |
[4] | 刘阳, 冮鹏, 赵少伟, 等. “老脚印” 对自升式钻井平台插桩滑移的影响研究[J]. 探矿工程-岩土钻掘工程, 2018, 45(6): 40-46. |
[4] | LIU Yang, GANG Peng, ZHAO Shaowei, et al. Influence of “old footprints” on pile slip of self-elevating drilling platform[J]. Exploration Engineering (Rock & Soil Drilling & Tunneling), 2018, 45(6): 40-46. |
[5] | 戴霖, 邓春林, 杨杰, 等. 平台就位过程滑桩研究及对策[J]. 中国水运, 2019, 19(6): 91-92. |
[5] | DAI Lin, DENG Chunlin, YANG Jie, et al. Research and countermeasures of sliding pile in the process of platform positioning[J]. China Water Transport, 2019, 19(6): 91-92. |
[6] | MAHANTA R. Punch-through analysis of jack-up rig at a site off the east coast of India—A case study[C]\\IV, A, MAJI V. Geotechnical Applications. Singapore: Springer, 2019: 283-290. |
[7] | BIENEN B, QIU G, PUCKER T. CPT correlation developed from numerical analysis to predict jack-up foundation penetration into sand overlying clay[J]. Ocean Engineering, 2015, 108: 216-226. |
[8] | 严维锋, 张峰, 叶俊放, 等. 南黄海铁板砂地层插桩分析及应对[J]. 海洋石油, 2021, 41(2): 115-120. |
[8] | YAN Weifeng, ZHANG Feng, YE Junfang, et al. Analysis and countermeasures of pile insertion in the iron plate sand stratum of the South Yellow Sea[J]. Offshore Oil, 2021, 41(2): 115-120. |
[9] | 陈庆, 谭伯兴. 胜利六号近海自升式移动钻井平台的插拔桩问题的研究[J]. 海洋工程, 1993, 11(4): 84-92. |
[9] | CHEN Qing, TAN Boxing. Study on problems in pulling up legs of offshore jack-up drilling platform-Shengli no. 6[J]. The Ocean Engineering, 1993, 11(4): 84-92. |
[10] | 赵文哲. 埕岛海区浅表层地质特点分析[J]. 海岸工程, 2005, 24(4): 27-34. |
[10] | ZHAO Wenzhe. Analysis of geologic characteristics of shallow strata in Chengdao sea area[J]. Coastal Engineering, 2005, 24(4): 27-34. |
[11] | 安有杰. 旧桩坑对自升式平台插桩稳定性的影响及对策[J]. 中国化工贸易, 2020, 12(15): 242-243. |
[11] | An Youjie. Influence of old pile pit on pile stability of jack-up platform and countermeasures[J]. China Chemical Trade, 2020, 12(15): 242-243. |
[12] | 佘稳. 海洋工程勘察中评价砂土液化势的方法研究[J]. 工程勘察, 2020, 48(2): 24-29. |
[12] | SHE Wen. Study on evaluating methods of liquefaction potential for sandy soil in marine engineering investigation[J]. Geotechnical Investigation & Surveying, 2020, 48(2): 24-29. |
[13] | 王虎刚. 浅谈海洋饱和砂土液化及判别方法[J]. 价值工程, 2014, 33(22): 317-319. |
[13] | WANG Hugang. On the liquefaction and identification methods of marine saturated sand[J]. Value Engineering, 2014, 33(22): 317-319. |
/
〈 |
|
〉 |