A finite element model for theoretical analysis was established to study the effect of slurry pressure on soil deformation control during pipe-jacking construction. Based on the comparison of measured data and finite element results, the influences of pore pressure and soil deformation during the construction process were discussed. The soil disturbance around pipe-jacking with different slurry pressures was analyzed, based on which the concept of pore pressure change rate was proposed. Taking the results of soil deformation and disturbance analysis into consideration, it is suggested that in practical engineering, the slurry pressure should be 1.1 times the overlying earth pressure, which has less impacts on the surrounding environment. This conclusion can provide reference for future similar pipe-jacking constructions.
CONG Mao-qiang, CHEN Jin-jian, WANG Jian-hua . Micro Disturbance Mechanism of Concrete Pipe-jacking with Slurry Pressure Control[J]. Journal of Shanghai Jiaotong University, 2013 , 47(06) : 867 -871 . DOI: 10.16183/j.cnki.jsjtu.2013.06.004
[1] | Li F B, Fang K, Li H C. Application of ANSYS 3D FEM in studies of surface deformation caused by pipe jacking[J]. Wuhan University Journal of Natural Sciences, 2007, 12(4): 633-637. |
[2] | LU Ai-zhong, XU Gui-sheng, SUN Feng, et al. Elasto-plastic analysis of a circular tunnel including the effect of the axial in situ stress[J]. International Journal of Rock Mechanics & Mining Sciences, 2010, 47(1): 50-59. |
[3] | ZHOU Song, WANG Ying-yi, HUANG Xing-chun. Experimental study on the effect of injecting slurry inside a jacking pipe tunnel in silt stratum[J]. Tunneling and Underground Space Technology, 2009, 24(4): 466-471. |
[4] | Shou K, Yen J, Liu M. On the frictional property of lubricants and its impact on jacking force and soil-pipe interaction of pipe-jacking[J]. Tunneling and Underground Space Technology, 2010, 25(4): 469-477. |
[5] | 魏纲, 徐日庆, 屠玮. 顶管施工引起的土体扰动理论分析及试验研究[J]. 岩石力学与工程学报, 2004, 23(3): 476-482. |
[5] | WEI Gang, XU Ri-qing, TU Wei. Testing study and analysis on soil disturbance induced by pipe jacking construction[J]. Chinese Journal of Rock Mechanics and Engineering, 2004, 23(3): 476-482. |
[6] | 黄吉龙, 陈锦剑, 王建华, 等. 大口径顶管顶进过程的数值模拟分析[J]. 地下空间与工程学报, 2008, 4(3): 489-493. |
[6] | HUANG Ji-long, CHEN Jin-jian, WANG Jian-hua, et al. Numerical analysis of large diameter pipe-jacking[J]. Chinese Journal of Underground Space and Engineering, 2008, 4(3): 489-493. |
[7] | 雷晗, 陈锦剑, 王建华, 等. 大直径砼顶管的管道受力特性分析[J]. 上海交通大学学报, 2011, 45(10): 1493-1497. |
[7] | LEI Han, CHEN Jin-jian, WANG Jian-hua, et al. Analysis on performance of large diameter concrete jacking pipe[J]. Journal of Shanghai Jiaotong University, 2011, 45(10): 1493-1497. |
[8] | 徐中华. 上海地区支护结构与主体地下结构相结合的深基坑变形性状研究[D]. 上海: 上海交通大学船舶海洋与建筑工程学院, 2007. |
/
〈 |
|
〉 |