On the background of 500 kV Shanghai Expo underground substation, a fluid-structure coupling FEM analysis of dewatering and excavation was made based on the Biot's consolidation theory. A pumping test was simulated to determine soil parameters by back-analysis of displacement and pore pressure. A fluid-structure coupling model was built to analyze dewatering and excavation with steady analysis method and birth-death element method respectively. Seepage and stress fields were solved at the same time. With comparison of the calculated and measured values, the fluid-structure coupling method used in the analysis of dewatering and excavation was proved to be correct and feasible.

Cite this article

LIU Jing, CHEN Jin-jian, WANG Jian-hua . Fluid-Structure Coupling Analysis of Dewatering and Excavation in 500 kV Shanghai Expo Underground Substation[J]. Journal of Shanghai Jiaotong University, 2010 , 44(06) : 721 -725 . DOI: 10.16183/j.cnki.jsjtu.2010.06.001

References

[1] 陶明星, 刘建民.基坑渗流的数值模拟与分析[J]. 工程勘察, 2006(1): 23-25.
[1] TAO Ming-xing, LIU Jian-min. Numeric analysis of the see page field in foundation[J]. Journal of Geotechnical Investigation & Surveying, 2006(1): 23-25.
[2] 陈锦剑, 范巍, 王建华.深基坑坑外降水引起土体沉降的有限元分析[J]. 岩土工程学报, 2006, 28(S1): 1346-1349.
[2] CHEN Jin-jian, FAN Wei, WANG Jian-hua. FEM analysis of settlement caused by dewatering in deep excavation[J]. Chinese Journal of Geotechnical Engineering, 2006, 28(S1):1346-1349.
[3] 何世秀, 胡其志, 庄心善.渗流对基坑周边沉降的影响[J]. 岩石力学与工程学报, 2003, 22(9): 1551-1554.
[3] HE Shi-xiu, HU Qi-zhi, ZHUANG Xin-shan. Influence of seepage on ground settlement of deep foundation pit[J]. Rock and Soil Mechanics, 2003, 22(9): 1551-1554.
[4] Gambolati G, Gatto P, Freeze R A.Mathematical simulation of the subsidence of Venice EM DASH[J]. Water Resources Research, 1974, 10(3): 563-577.
[5] 唐翠萍, 许烨霜, 沈水龙, 等.基坑开挖中地下水抽取对周围环境的影响分析[J]. 地下空间与工程学报, 2005, 4(1): 634-637.
[5] TANG Cui-ping, XU Ye-shuang, SHEN Shui-long, et al. Impact analysis of groundwater withdrawal during excavation of a deep foundation pit[J]. Chinese Journal of Underground Space and Engineering, 2005, 4(1): 634-637.
[6] Lewis R W, Schrefler B. A fully coupled consolidation model of the subsidence of Venice[J]. Water Resource Research, 1978, 14(2): 465-473.
Outlines

/