中重冰区电网架空输电线路工程造价风险评估方法

展开
  • 1. 国网湖南省电力有限公司经济技术研究院,长沙 410004;2. 能源互联网供需运营湖南省重点实验室,长沙 410004;3. 国网湖南省电力有限公司,长沙 410007;4. 湖南大学电气与信息工程学院,长沙 410082
陈屹东(1990—),高级经济师,从事电力技术经济与电力工程造价管理研究。
周斌,教授,博士生导师;E-mail:binzhou@hnu.edu.cn。

网络出版日期: 2026-10-11

基金资助

国网湖南省电力有限公司专业咨询项目(B616A225Z006)

Cost Risk Assessment Method for Overhead Transmission Line Project in Medium and Heavy Ice Areas

Expand
  • 1. Economic and Technical Research Institute, State Grid Hunan Electric Power Co. , Ltd, Changsha 410004;2. Hunan Key Laboratory of Energy Internet Supply-Demand and Operation, Changsha 410004;3. State Grid Hunan Electric Power Co. , Ltd, Changsha 410007;4. College of Electrical and Information Engineering, Hunan University, Changsha 410082

Online published: 2026-10-11

摘要

本文提出一种基于贝叶斯深度神经网络的中重冰区架空输电线路工程造价风险评估方法。首先,分析了冰区电网架空输电线路造价构成机理,以及关键工程属性、外部环境因素对各分项造价的差异化影响,构建了涵盖关键工程属性与外部环境因素的中重冰区架空输电线路工程造价影响因素集,建立了中重冰区架空输电线路工程造价测算模型。其次,考虑关键工程属性、外部环境因素与各分项造价之间的非线性耦合关系,提出了中重冰区架空输电线路工程造价超支风险,构建了多维因素输入和多分项造价输出的贝叶斯深度神经网络联合预测框架,有效评估了中重冰区架空输电线路造价超支风险概率。最后,以中部某省中重冰区976组实际架空输电线路工程造价数据为例进行对比分析与超支风险评估,结果表明所提方法可有效评估中重冰区架空输电线路工程造价风险。

本文引用格式

陈屹东, 李金茗, 胡伟, 汤健, 陈梓炀, 邓嘉翕, 李帅康, 周斌 . 中重冰区电网架空输电线路工程造价风险评估方法[J]. 上海交通大学学报, 0 : 1 . DOI: 10.16183/j.cnki.jsjtu.2026.162

Abstract

This paper proposes a Bayesian deep neural network-based cost risk assessment method for overhead transmission line projects in medium and heavy ice areas. First, the cost formation mechanism and the differentiated effects of key engineering attributes and external environmental factors on individual cost components are analyzed. A cost influencing factor set and a cost estimation model are established. Second, considering the nonlinear coupling among engineering attributes, environmental factors, and cost components, cost overrun risk is defined, and a Bayesian deep neural network-based joint prediction framework with multidimensional inputs and multiple cost-component outputs is developed to assess cost overrun probabilities. Finally, comparative analysis and cost overrun risk assessment are conducted using 976 actual project cost datasets from a central Chinese province. The results demonstrate the effectiveness of the proposed method in assessing the cost risks of overhead transmission line projects in medium and heavy ice areas.